A Website and MRV Dashboard for Carbon Removal at Wastewater Plants
The alkamycarbon.com website and a plant portal for its mineral dosing system: live inlet and outlet chemistry, automated dosing, and a carbon-removal ledger where every tonne traces back to measured readings.
Pilot plant A
Activated-sludge plant · 40 MLD · mineral dosing since 2 Sep · live
CO₂ removed, Nov
38.4 t
+12% vs Oct
Outlet pH
7.4
target 7.2–7.6
Dosing uptime
99.2%
1 stop, 20 min
Batches verified
26 / 28
2 pending lab check
The gap between outlet and inlet is the carbon stored as bicarbonate.
Inlet pH6.9
Outlet pH7.4
Alkalinity out212 mg/L
Flow1,640 m³/h
Dose rate118 kg/h
Sensors6 / 6 online
- Client
- Alkamy Carbon
- Location
- India
- Website
- alkamycarbon.com
- Sector
- Climate · carbon removal
- Service
- Build With Us
- Duration
- 12 weeks
- Team
- 4 people: PM, designer, full-stack dev, data engineer
- Built with
- Next.jsTypeScriptPython (FastAPI)TimescaleDBMQTTAWS
- chemistry measured continuously, per plant
- Inlet + outletchemistry measured continuously, per plant
- tonne traceable to measured readings
- Everytonne traceable to measured readings
- portal for dosing, monitoring and MRV
- 1portal for dosing, monitoring and MRV
- at alkamycarbon.com
- Liveat alkamycarbon.com
01 · About the client
Alkamy Carbon turns wastewater treatment into a carbon sink. Natural minerals, dosed precisely into a plant's existing process, stabilise treatment chemistry while converting dissolved CO₂ into stable bicarbonates: permanent, measurable carbon removal. Inlet and outlet sensing measures the change directly, so every credit is traceable, and the credits fund deployment, so utilities pay nothing to take part. The company was founded by Rushil Hari Koppaka and Rishi Rathi.
02 · The problem
- 01
A new idea for conservative buyers.
Utility engineers had to see quickly that it needs no process changes and costs them nothing.
- 02
Removal has to be measured.
Carbon buyers trust only credits backed by continuous, traceable measurement.
- 03
Plants run all day, every day.
Dosing and monitoring had to work without anyone watching a screen.
- 04
Pilots start with a conversation.
Partner enquiries had to reach the founders with the details a pilot needs.
03 · Our solution
We built alkamycarbon.com and a portal for the plants. The website explains the idea in one scroll: the chemistry, the benefits for the plant, why the carbon removal is permanent and verifiable, and a partner form that asks for flow, plant type and location. The portal shows each plant's inlet and outlet chemistry live, the dosing rate and how the optimiser has adjusted it, and alerts when a reading drifts. Every batch of treated water becomes a line in the carbon-removal ledger, with the readings behind it, and verified batches export as an MRV report for the registry.
04 · What we built
Explainer website
Chemistry, plant benefits and verifiable removal in one scroll, with partner enquiries.
Live plant chemistry
Inlet and outlet pH, alkalinity and dissolved carbon, per plant.
Dosing and optimisation
Dose rate, set limits and every automatic adjustment, logged.
Alerts
Sensor drift, dosing faults and out-of-range readings, sent to the operator.
Carbon-removal ledger
Each batch with the measurements behind it and its verification status.
MRV export
Verified batches packaged for the registry and the credit buyer.
Building climate tech that has to prove its numbers?
05 · Challenges we solved
- 1
Data you can audit
Raw sensor readings are kept unchanged beside the calculated removal, so a verifier can recompute any batch.
- 2
Patchy plant connectivity
Gateways buffer readings locally and sync when the link returns, with no gaps in the record.
- 3
Plain language for utilities
The website talks about treatment, cost and safety first, and carbon second.
06 · Our approach
Weeks 1–2
01 Discovery
Mapped the chemistry, the sensors and what a verifier needs to see.
Weeks 3–4
02 Website
Built the one-scroll site and the partner form.
Weeks 5–10
03 Portal
Live chemistry, dosing logs, alerts and the ledger in two-week sprints.
Weeks 11–12
04 Pilot-ready
Connected the first pilot plant and tested the MRV export.
07 · Results
Alkamy has a website that explains carbon removal at a treatment plant in terms a utility engineer cares about, and a portal where every tonne it claims can be traced back to the readings that prove it.
Inside the work.
Screenshots from the live work. Click any screen to enlarge.
Related work.
- console.heliousai.com/overview
Today's passes
Exercise area North · 6 passes · 18,420 frames · all times IST
New flight planPasses today
6
2 areas
Frames uploaded
18,420
98.6% verified
Composites ready
4
1 running
Signatures to review
11
none confirmed yet
PassesNewest firstPassAreaPatternAlt.FramesUploadStatusP-0412Sector A-14Lawnmower35 m3,072100%ReadyP-0411Sector A-14Spiral40 m2,880100%ReadyP-0410Sector C-02Lawnmower35 m3,114100%RunningP-0409Sector C-02Lawnmower30 m3,206100%ReadyP-0408Sector B-07Spiral40 m2,64072%UploadingP-0407Sector B-07Lawnmower35 m3,5080%QueuedDefence · AI imaging · India
Build With Us
A Website and Mission Console for Canopy-Penetrating Defence AI
The heliousai.com website and a secure mission console for E-AOS imaging: flight planning, upload tracking, multi-layer reconstruction runs and ground composites whose AI detections an operator reviews.
- steps from flight to ground composite, on one console
- 4steps from flight to ground composite, on one console
- of geotagged thermal frames per pass, handled for the operator
- 1,000sof geotagged thermal frames per pass, handled for the operator
- detection reviewed by a person
- Everydetection reviewed by a person
- app.cityverseai.com/portfolio
Capital projects portfolio
Sample City · FY2026–27 · 18 active projects
ExportNew projectActive projects
18
6 in construction
In design review
5
2 resubmittals due
Findings to decide
7
1 fail · 1 needs judgment
Spent vs budget
41%
$11.6M of $28.4M
ProjectsSorted by next deadlineProjectPhaseBudgetSpentStatusElm St. Reconstruction60% plans$4.8M18%Cycle 2 · 7 findingsNorth Basin Sewer LiningConstruction$2.1M64%Field ops dailyRiverside Water Main, Ph. 290% plans$6.3M31%Cycle 3 · 2 findingsOak Ave. ADA RampsConstruction$0.9M82%Punch listHarbor Rd. ResurfacingPreliminary$3.4M6%Specs draftingPine St. Storm Drain60% plans$1.7M15%Resubmittal lateWestgate Lift StationBid$5.2M9%Bid opens 4 DecGovTech · capital projects · United States
Build With Us
A Website and Portal for an AI Operating Layer for City Capital Projects
The cityverseai.com website and the portal for its platform: a capital-projects portfolio, Themis plan review against a city's standard plates, questions answered across specifications with sources, and field reports from a phone.
- everyday project tasks on one platform
- 6everyday project tasks on one platform
- products: Themis and Field Operations
- 2products: Themis and Field Operations
- finding cites its sheet or section
- Everyfinding cites its sheet or section
- app.doclarity.eu/dokumente
Dokumente
November 2026 · 46 Dokumente · 1.284 Seiten
HochladenDokumente
46
diesen Monat
Seiten
1.284
barrierefrei gemacht
PDF/UA-Prüfung
44 / 46
maschinell bestanden
Seiten übrig
716
von 2.000 im Plan
Zuletzt hochgeladenPDF, Word, PowerPoint, LibreOfficeDateiSeitenStatusPDF/UAJahresbericht_2025.pdf48Bereit zur PrüfungBestandenAntrag_Wohnbeihilfe.docx6Wird bearbeitet · 64%—Gemeinderat_Protokoll_Okt.pdf22HeruntergeladenBestandenLeitfaden_Barrierefreiheit.pptx31HeruntergeladenBestandenBudget_2026_Scan.pdf64Bereit zur Prüfung2 HinweiseBebauungsplan_Nord.pdf12HeruntergeladenBestandenAbfallkalender_2026.pdf4HeruntergeladenBestandenAI · digital accessibility · Austria
Build With Us
A Bilingual Website and Portal for AI-Made Accessible PDFs
The English and German doclarity.eu website and the account portal for its AI remediation: upload a PDF or Office file, set the rules once, check every suggested tag before download, and see each file's PDF/UA machine check.
- languages: English and German, site and portal
- 2languages: English and German, site and portal
- contrast levels to fix to: WCAG A, AA or AAA
- 3contrast levels to fix to: WCAG A, AA or AAA
- machine check on every file, shown before download
- PDF/UAmachine check on every file, shown before download
Get in touch
Building climate tech that has to prove its numbers?
Share a few lines about your idea, workflow or project. A senior lead replies within one business day.
- Free 30-minute strategy call
- NDA on request
- Proposal within 48 hours
The right conversation can save you
six months.
Free 30-minute strategy call · NDA on request · Proposal within 48 hours